Northern Memorial Park - River Red Gum Stage 2 Update

Following the holiday break, we’ve recommenced work on the River Red Gum Stage 2 project and have some important updates for our community.

Soil Mound Removal

Start Date: 12 January 2026

Duration: Approximately 4-6 months

Next week, our contractor will begin removing the large soil mound currently on-site. We know this has been a significant concern for residents, both visually and due to dust. Its removal is an important step toward improving the environment and responding to your feedback.

What you can expect:

  • Removal will start from the rear of the site (approx. 180m from nearest homes) and progress in stages.

  • Water carts will be used consistently at the soil loading area.

  • Trucks travelling along May Street will have loads securely covered.

  • Dust suppression measures will continue throughout the process.

Andrew Street Sewer Upgrade

Timing: End of January to early February 2026 (approx. 1 week, weather permitting)

Construction Hours: 7am – 5pm

Following the May Street entrance upgrades last year, we’ll upgrade the sewer connection to integrate Northern Memorial Park’s system with the municipal network — helping future-proof essential infrastructure.

During these works:

  • Access will be restricted to local traffic only, with traffic controllers on-site.

  • A lane closure will be in place along Andrew Street.

  • The southern footpath on Andrew Street will remain closed outside working hours until works are complete.

Stay Updated

Visit our Community Engagement Hub, YourSay for ongoing updates, or email community@gmct.com.au if you have any questions or feedback.

Thank you for your patience and understanding as we deliver these improvements.